| DDR-24365 | 7 Oct day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2619 | 182.1 → 235.9 | 53.8 | 11.5 / 0 | $9,842 | Approved | |
| DDR-24354 | 6 Oct day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2619 | 131.2 → 182.1 | 50.9 | 11 / 0 | $9,067 | Approved | |
| DDR-24343 | 5 Oct day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2619 | 84.9 → 131.2 | 46.3 | 11.5 / 0 | $8,250 | Approved | |
| DDR-24332 | 4 Oct day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2619 | 43.7 → 84.9 | 41.2 | 11 / 0 | $7,760 | Approved · invoiced | |
| DDR-24326 | 3 Oct day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2619 | 0 → 43.7 | 43.7 | 11.5 / 0 | $7,776 | Approved · invoiced | |
| DDR-24315 | 2 Oct day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2617 | 371.6 → 374 | 2.4 | 6.5 / 0 | $2,853 | Approved · invoiced | |
| DDR-24304 | 1 Oct day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2617 | 341.4 → 371.6 | 30.2 | 11.5 / 0 | $6,377 | Approved · invoiced | |
| DDR-24293 | 30 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2617 | 297.3 → 341.4 | 44.1 | 11.5 / 0 | $9,115 | Approved · invoiced | |
| DDR-24282 | 29 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2617 | 258.8 → 297.3 | 38.5 | 10.5 / 1 | $7,665 | Approved · invoiced | |
| DDR-24271 | 28 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2617 | 212.1 → 258.8 | 46.7 | 9.5 / 1.5 | $9,325 | Approved · invoiced | |
| DDR-24261 | 27 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2617 | 167.9 → 212.1 | 44.2 | 11 / 0 | $8,138 | Approved · invoiced | |
| DDR-24255 | 26 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2617 | 117.4 → 167.9 | 50.5 | 11.5 / 0 | $9,412 | Approved · invoiced | |
| DDR-24245 | 25 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2617 | 73.5 → 117.4 | 43.9 | 11.5 / 0 | $8,225 | Approved · invoiced | |
| DDR-24235 | 24 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2617 | 38.6 → 73.5 | 34.9 | 11 / 0 | $6,625 | Approved · invoiced | |
| DDR-24224 | 23 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2617 | 0 → 38.6 | 38.6 | 8 / 3 | $8,334 | Approved · invoiced | |
| DDR-24213 | 22 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2615 | 326.7 → 337 | 10.3 | 11.5 / 0 | $2,442 | Approved · invoiced | |
| DDR-24202 | 21 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2615 | 296.2 → 326.7 | 30.5 | 9.5 / 1.5 | $7,006 | Approved · invoiced | |
| DDR-24191 | 20 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2615 | 274.3 → 296.2 | 21.9 | 7.5 / 4 | $5,891 | Approved · invoiced | |
| DDR-24185 | 19 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2615 | 247.3 → 274.3 | 27.0 | 10 / 1.5 | $5,393 | Approved · invoiced | |
| DDR-24176 | 18 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2615 | 190.6 → 247.3 | 56.7 | 11.5 / 0 | $10,297 | Approved · invoiced | |
| DDR-24167 | 17 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2615 | 150.7 → 190.6 | 39.9 | 11.5 / 0 | $7,511 | Approved · invoiced | |
| DDR-24158 | 16 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2615 | 95.7 → 150.7 | 55.0 | 11.5 / 0 | $10,212 | Approved · invoiced | |
| DDR-24149 | 15 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2615 | 63.1 → 95.7 | 32.6 | 11.5 / 0 | $6,022 | Approved · invoiced | |
| DDR-24140 | 14 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2615 | 28.9 → 63.1 | 34.2 | 11.5 / 0 | $6,504 | Approved · invoiced | |
| DDR-24131 | 13 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2615 | 0 → 28.9 | 28.9 | 11 / 0 | $5,429 | Approved · invoiced | |
| DDR-24127 | 12 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2613 | 339.2 → 345 | 5.8 | 6 / 0 | $3,753 | Approved · invoiced | |
| DDR-24121 | 11 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2613 | 305 → 339.2 | 34.2 | 11 / 0 | $7,118 | Approved · invoiced | |
| DDR-24115 | 10 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2613 | 259 → 305 | 46.0 | 11 / 0 | $8,594 | Approved · invoiced | |
| DDR-24109 | 9 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2613 | 220.5 → 259 | 38.5 | 8.5 / 2.5 | $8,120 | Approved · invoiced | |
| DDR-24103 | 8 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2613 | 169.9 → 220.5 | 50.6 | 11.5 / 0 | $9,015 | Approved · invoiced | |
| DDR-24097 | 7 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2613 | 144.9 → 169.9 | 25.0 | 8 / 3 | $5,848 | Approved · invoiced | |
| DDR-24092 | 6 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2613 | 96.9 → 144.9 | 48.0 | 11 / 0 | $8,542 | Approved · invoiced | |
| DDR-24088 | 5 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2613 | 63.7 → 96.9 | 33.2 | 11 / 0 | $6,332 | Approved · invoiced | |
| DDR-24083 | 4 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2613 | 35.3 → 63.7 | 28.4 | 11 / 0 | $5,067 | Approved · invoiced | |
| DDR-24078 | 3 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2613 | 0 → 35.3 | 35.3 | 11 / 0 | $6,487 | Approved · invoiced | |
| DDR-24073 | 2 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2611 | 312.5 → 331 | 18.5 | 11.5 / 0 | $4,101 | Approved · invoiced | |
| DDR-24068 | 1 Sep day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2611 | 272.7 → 312.5 | 39.8 | 11.5 / 0 | $7,794 | Approved · invoiced | |
| DDR-24063 | 31 Aug day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2611 | 226.7 → 272.7 | 46.0 | 11 / 0 | $8,612 | Approved · invoiced | |
| DDR-24060 | 30 Aug day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2611 | 190.6 → 226.7 | 36.1 | 11.5 / 0 | $6,788 | Approved · invoiced | |
| DDR-24057 | 29 Aug day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2611 | 140.7 → 190.6 | 49.9 | 11.5 / 0 | $9,102 | Approved · invoiced | |
| DDR-24054 | 28 Aug day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2611 | 108.6 → 140.7 | 32.1 | 11.5 / 0 | $5,729 | Approved · invoiced | |
| DDR-24051 | 27 Aug day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2611 | 65 → 108.6 | 43.6 | 11.5 / 0 | $8,104 | Approved · invoiced | |
| DDR-24048 | 26 Aug day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2611 | 11.3 → 65 | 53.7 | 11.5 / 0 | $9,893 | Approved · invoiced | |
| DDR-24045 | 25 Aug day | R205 | KP-26-031 BHP Mt Arthur Coal | MTA2611 | 0 → 11.3 | 11.3 | 3.5 / 2 | $5,392 | Approved · invoiced | |