DDR submitted — R204 night shiftMt Arthur night crew sent their drill report for 08 Oct. Waiting for approval.09 Oct 2026 · 06:41Gas test ticket expired
Corey Albrecht (R212, Maxwell gas drainage) — gas test atmospheres lapsed 01 Oct.09 Oct 2026 · 06:126 drill reports submitted
Day shift reports from R201, R205, R208, R210, R212 and R218.08 Oct 2026 · 18:22Stock below reorder point
HQ Series 9 bits at Muswellbrook — 7 on hand, reorder at 10.08 Oct 2026 · 15:30Incident KS-26-091 reported
R212 hydraulic hose burst on the top drive at Maxwell. No injury.07 Oct 2026 · 16:05Drill report queried
Boggabri 07 Oct — 3.5 h standby not on the client sheet.07 Oct 2026 · 09:20Quote accepted — KQ-26-131
Mid-Western Regional Council accepted the Gulgong production bore. Project KP-26-045 set up.06 Oct 2026 · 11:05Weekly invoices raised
w/e 04 Oct — drilling invoices raised and synced to Xero.06 Oct 2026 · 08:40Plant off-hired — E018
Orange City Council off-hired the tractor slasher. Ready to invoice.03 Oct 2026 · 15:10Invoice overdue
Geoglide — final geotech invoice is past due.01 Oct 2026 · 09:00
Activity
Brett Hollis submitted the 08 Oct night shift from the rig R20409 Oct 2026 · 06:41Corey Albrecht submitted the 08 Oct day shift R21208 Oct 2026 · 18:22Ross Gallagher drafted PPE order for Orange PO-26-041808 Oct 2026 · 14:02Brooke Fennell approved 9 day-shift reports — timesheets and stock updated 07 Oct08 Oct 2026 · 09:30Corey Albrecht reported a hydraulic hose failure on R212 KS-26-09107 Oct 2026 · 16:05Shane Wilkes sent the R212 hose kit order to Hunter Hydraulics PO-26-041707 Oct 2026 · 11:48Lisa Chandler accepted online — order MWRC-PO-88412 KQ-26-13106 Oct 2026 · 11:05Kylie Hartmann raised weekly drilling invoices and synced to Xero w/e 04 Oct06 Oct 2026 · 08:40Kylie Hartmann exported timesheets to payroll w/e 04 Oct06 Oct 2026 · 07:55Matt Rourke booked pre-mob service before Bowdens R22005 Oct 2026 · 10:20