All drill reports Rig app
Metres drilled (approved)
567 / 660 m
86% · 3 of 4 holes complete
Contract value
$162,624
ex GST
Earned to date
$123,046
16 approved shifts
Margin to date
38.0%
$46,710 after crew, rig & consumables
Standby
2 h
173 h drilling
Ready to invoice — 0 approved shifts not yet billed · invoiced to date $139,546 $0
Holes3 complete · 1 drilling · 0 planned
HoleRigSizeDepth%CollaredCompletedStatus
ASH001 R201 HQ3 165 / 165 m 100 04 Aug 2026 08 Aug 2026 Complete
ASH002 R201 HQ3 165 / 165 m 100 10 Aug 2026 13 Aug 2026 Complete
ASH003 R201 HQ3 165 / 165 m 100 14 Aug 2026 19 Aug 2026 Complete
ASH004 R201 HQ3 71.8 / 165 m 44 20 Aug 2026 — Drilling
Latest drill reportsAll →
ReportShiftRigHoleMetresStby hValueStatus
DDR-2404221 Aug dayR201ASH00434.32$8,080Approved · invoiced
DDR-2404020 Aug dayR201ASH00437.50$7,922Approved · invoiced
DDR-2403719 Aug dayR201ASH00315.20$3,220Approved · invoiced
DDR-2403418 Aug dayR201ASH00331.40$6,619Approved · invoiced
DDR-2403117 Aug dayR201ASH00331.40$6,619Approved · invoiced
DDR-2402715 Aug dayR201ASH00337.90$8,004Approved · invoiced
DDR-2402414 Aug dayR201ASH00349.10$10,352Approved · invoiced
DDR-2402113 Aug dayR201ASH00211.90$2,518Approved · invoiced
DDR-2401812 Aug dayR201ASH00254.00$11,382Approved · invoiced
DDR-2401511 Aug dayR201ASH00251.70$10,911Approved · invoiced
DDR-2401210 Aug dayR201ASH00247.40$10,003Approved · invoiced
DDR-240108 Aug dayR201ASH00117.00$3,589Approved · invoiced
DDR-240087 Aug dayR201ASH00155.20$11,654Approved · invoiced
DDR-240066 Aug dayR201ASH00129.50$6,230Approved · invoiced
DDR-240045 Aug dayR201ASH00148.10$10,147Approved · invoiced
DDR-240024 Aug dayR201ASH00115.20$5,800Approved · invoiced
Schedule of rateswhat every drill report is valued against
CodeDescriptionUnitRateApplied to
MOB-CORE Mobilise & demobilise — core rig lump $16,500.00 lump
DRL-HQ HQ3 wireline core 0–300 m m $205.00 metre
STBY Standby — rig & crew hr $420.00 standby
MOVE Rig move between holes hr $430.00 move
CT-HQ Core trays — HQ ea $26.00 item:CT-HQ
Client
Yancoal Australia
Site
Ashton Coal
Client rep
Priya Nair
PO
4700-22816
Terms
30 days EOM
Supervisor
Warren Kelly
Dates
04 Aug 2026 – 21 Aug 2026
Rigs
R201
Site access: Underground — surface works only.
Final invoice issued.