Kerembla

KP-26-040

Regis Resources — Resource definition — RC, McPhillamys pit shell
Xero · synced 09:14 Demo 09 Oct 2026
← Projects Drilling RC · Resource definition · Orange depot
All drill reports Rig app
Metres drilled (approved)
3,331 / 6,000 m
56% · 15 of 30 holes complete
Contract value
$614,160
ex GST
Earned to date
$318,536
32 approved shifts
Margin to date
43.6%
$138,908 after crew, rig & consumables
Standby
12.5 h
333.5 h drilling
Ready to invoice — 3 approved shifts not yet billed · invoiced to date $298,877 $28,659
Holes15 complete · 1 drilling · 14 planned
HoleRigSizeDepth%CollaredCompletedStatus
MPR001 R218 140 mm 250 / 250 m 100 01 Sep 2026 03 Sep 2026 Complete
MPR002 R218 140 mm 210 / 210 m 100 04 Sep 2026 05 Sep 2026 Complete
MPR003 R218 140 mm 215 / 215 m 100 07 Sep 2026 08 Sep 2026 Complete
MPR004 R218 140 mm 196 / 196 m 100 09 Sep 2026 10 Sep 2026 Complete
MPR005 R218 140 mm 160 / 160 m 100 11 Sep 2026 11 Sep 2026 Complete
MPR006 R218 140 mm 226 / 226 m 100 12 Sep 2026 14 Sep 2026 Complete
MPR007 R218 140 mm 190 / 190 m 100 15 Sep 2026 16 Sep 2026 Complete
MPR008 R218 140 mm 165 / 165 m 100 17 Sep 2026 18 Sep 2026 Complete
MPR009 R218 140 mm 236 / 236 m 100 19 Sep 2026 21 Sep 2026 Complete
MPR010 R218 140 mm 173 / 173 m 100 22 Sep 2026 23 Sep 2026 Complete
MPR011 R218 140 mm 161 / 161 m 100 24 Sep 2026 25 Sep 2026 Complete
MPR012 R218 140 mm 200 / 200 m 100 26 Sep 2026 28 Sep 2026 Complete
MPR013 R218 140 mm 254 / 254 m 100 29 Sep 2026 30 Sep 2026 Complete
MPR014 R218 140 mm 238 / 238 m 100 01 Oct 2026 02 Oct 2026 Complete
MPR015 R218 140 mm 239 / 239 m 100 03 Oct 2026 05 Oct 2026 Complete
MPR016 R218 140 mm 217.5 / 232 m 94 06 Oct 2026 — Drilling
MPR017 R218 140 mm 0 / 177 m 0 — — Planned
MPR018 R218 140 mm 0 / 224 m 0 — — Planned
MPR019 R218 140 mm 0 / 185 m 0 — — Planned
MPR020 R218 140 mm 0 / 187 m 0 — — Planned
MPR021 R218 140 mm 0 / 173 m 0 — — Planned
MPR022 R218 140 mm 0 / 172 m 0 — — Planned
MPR023 R218 140 mm 0 / 160 m 0 — — Planned
MPR024 R218 140 mm 0 / 239 m 0 — — Planned
MPR025 R218 140 mm 0 / 172 m 0 — — Planned
MPR026 R218 140 mm 0 / 189 m 0 — — Planned
MPR027 R218 140 mm 0 / 239 m 0 — — Planned
MPR028 R218 140 mm 0 / 180 m 0 — — Planned
MPR029 R218 140 mm 0 / 205 m 0 — — Planned
MPR030 R218 140 mm 0 / 197 m 0 — — Planned
Latest drill reportsAll →
ReportShiftRigHoleMetresStby hValueStatus
DDR-243708 Oct dayR218MPR01614.50—Submitted
DDR-243597 Oct dayR218MPR016112.93$11,647Approved
DDR-243486 Oct dayR218MPR016104.62.5$10,673Approved
DDR-243375 Oct dayR218MPR01568.90$6,339Approved
DDR-243203 Oct dayR218MPR015170.10$15,649Approved · invoiced
DDR-243092 Oct dayR218MPR014106.20$9,770Approved · invoiced
DDR-242981 Oct dayR218MPR014131.80$12,126Approved · invoiced
DDR-2428730 Sep dayR218MPR01399.40$9,145Approved · invoiced
DDR-2427629 Sep dayR218MPR013154.60$14,223Approved · invoiced
DDR-2426628 Sep dayR218MPR01238.60$3,551Approved · invoiced
DDR-2425026 Sep dayR218MPR012161.40$14,849Approved · invoiced
DDR-2424025 Sep dayR218MPR01141.10$3,781Approved · invoiced
DDR-2422924 Sep dayR218MPR011119.90$11,031Approved · invoiced
DDR-2421823 Sep dayR218MPR01043.33$5,244Approved · invoiced
DDR-2420722 Sep dayR218MPR010129.70$11,932Approved · invoiced
DDR-2419621 Sep dayR218MPR009120.60$11,095Approved · invoiced
Schedule of rateswhat every drill report is valued against
CodeDescriptionUnitRateApplied to
MOB-RC Mobilise & demobilise — RC rig lump $18,000.00 lump
DRL-RC RC 5½" face-sampling hammer m $92.00 metre
STBY Standby — rig & crew hr $420.00 standby
MOVE Rig move between holes hr $430.00 move
Client
Regis Resources
Site
McPhillamys Gold Project
Client rep
Daniel Ferreira
PO
RR-55120
Terms
30 days EOM
Supervisor
Luke Bramble
Dates
01 Sep 2026 – 18 Dec 2026
Rigs
R218
Site access: RC samples to the Regis core farm by 4 pm.