Xero · synced 09:14 Demo 09 Oct 2026
← Projects Drilling Rotary — water bore · Water bores and de-watering bores · Orange depot
All drill reports Rig app
Metres drilled (approved)
600 / 750 m
80% · 4 of 5 holes complete
Contract value
$179,600
ex GST
Earned to date
$181,254
15 approved shifts
Margin to date
45.3%
$82,163 after crew, rig & consumables
Standby
1.5 h
157 h drilling
Ready to invoice — 3 approved shifts not yet billed · invoiced to date $150,769 $35,235
Holes4 complete · 0 drilling · 1 planned
HoleRigSizeDepth%CollaredCompletedStatus
TGW001 R210 250 mm 150 / 150 m 100 21 Sep 2026 24 Sep 2026 Complete
TGW002 R210 250 mm 150 / 150 m 100 25 Sep 2026 28 Sep 2026 Complete
TGW003 R210 250 mm 150 / 150 m 100 29 Sep 2026 02 Oct 2026 Complete
TGW004 R210 250 mm 150 / 150 m 100 03 Oct 2026 07 Oct 2026 Complete
TGW005 R210 250 mm 0 / 150 m 0 — — Planned
Latest drill reportsAll →
ReportShiftRigHoleMetresStby hValueStatus
DDR-243698 Oct dayR210TGW00548.00—Submitted
DDR-243587 Oct dayR210TGW00421.90$17,595Approved
DDR-243476 Oct dayR210TGW00449.70$10,437Approved
DDR-243365 Oct dayR210TGW00434.30$7,203Approved
DDR-243193 Oct dayR210TGW00444.10$9,261Approved · invoiced
DDR-243082 Oct dayR210TGW0036.70$15,948Approved · invoiced
DDR-242971 Oct dayR210TGW00343.71.5$9,807Approved · invoiced
DDR-2428630 Sep dayR210TGW00350.80$10,668Approved · invoiced
DDR-2427529 Sep dayR210TGW00348.80$10,248Approved · invoiced
DDR-2426528 Sep dayR210TGW00240.30$20,827Approved · invoiced
DDR-2424926 Sep dayR210TGW00254.90$11,529Approved · invoiced
DDR-2423925 Sep dayR210TGW00254.80$11,508Approved · invoiced
DDR-2422824 Sep dayR210TGW00129.00$18,233Approved · invoiced
DDR-2421723 Sep dayR210TGW00145.80$9,618Approved · invoiced
DDR-2420622 Sep dayR210TGW00154.50$11,445Approved · invoiced
DDR-2419521 Sep dayR210TGW00120.70$6,927Approved · invoiced
Schedule of rateswhat every drill report is valued against
CodeDescriptionUnitRateApplied to
MOB-WB Mobilise & demobilise — water bore rig lump $9,500.00 lump
DRL-WB Rotary — 250 mm water bore m $210.00 metre
STBY Standby — rig & crew hr $420.00 standby
MOVE Rig move between holes hr $430.00 move
CAS-STL 200 mm steel casing m $118.00 item:CAS-STL
GRAVEL Gravel pack bag $38.00 item:GRAVEL
GROUT Cement grout bag $29.00 item:GROUT
Client
Alkane Resources
Site
Tomingley Gold Operations
Client rep
Kate O'Sullivan
PO
ALK-60433
Terms
30 days
Supervisor
Luke Bramble
Dates
21 Sep 2026 – 30 Oct 2026
Rigs
R210
Site access: Alkane induction. Bores discharge to TSF only.