Kerembla

KP-26-031

BHP Mt Arthur Coal — North pit exploration infill — HQ3 diamond
Xero · synced 09:14 Demo 09 Oct 2026
← Projects Drilling HQ3 core · Mineral exploration · Muswellbrook depot
All drill reports Rig app
Metres drilled (approved)
5,031 / 10,080 m
50% · 13 of 28 holes complete
Contract value
$2,088,520
ex GST
Earned to date
$984,434
132 approved shifts
Margin to date
33.2%
$326,928 after crew, rig & consumables
Standby
60.5 h
1,408 h drilling
Ready to invoice — 9 approved shifts not yet billed · invoiced to date $921,036 $71,648
Holes13 complete · 2 drilling · 13 planned
HoleRigSizeDepth%CollaredCompletedStatus
MTA2610 R204 HQ3 397 / 397 m 100 25 Aug 2026 30 Aug 2026 Complete
MTA2611 R205 HQ3 331 / 331 m 100 25 Aug 2026 02 Sep 2026 Complete
MTA2612 R204 HQ3 339 / 339 m 100 30 Aug 2026 04 Sep 2026 Complete
MTA2613 R205 HQ3 345 / 345 m 100 03 Sep 2026 12 Sep 2026 Complete
MTA2614 R204 HQ3 383 / 383 m 100 04 Sep 2026 08 Sep 2026 Complete
MTA2615 R205 HQ3 337 / 337 m 100 13 Sep 2026 22 Sep 2026 Complete
MTA2616 R204 HQ3 350 / 350 m 100 09 Sep 2026 13 Sep 2026 Complete
MTA2617 R205 HQ3 374 / 374 m 100 23 Sep 2026 02 Oct 2026 Complete
MTA2618 R204 HQ3 397 / 397 m 100 14 Sep 2026 18 Sep 2026 Complete
MTA2619 R205 HQ3 235.9 / 384 m 61 03 Oct 2026 — Drilling
MTA2620 R204 HQ3 340 / 340 m 100 19 Sep 2026 23 Sep 2026 Complete
MTA2621 R205 HQ3 0 / 340 m 0 — — Planned
MTA2622 R204 HQ3 388 / 388 m 100 23 Sep 2026 28 Sep 2026 Complete
MTA2623 R205 HQ3 0 / 384 m 0 — — Planned
MTA2624 R204 HQ3 398 / 398 m 100 28 Sep 2026 02 Oct 2026 Complete
MTA2625 R205 HQ3 0 / 351 m 0 — — Planned
MTA2626 R204 HQ3 331 / 331 m 100 03 Oct 2026 06 Oct 2026 Complete
MTA2627 R205 HQ3 0 / 373 m 0 — — Planned
MTA2628 R204 HQ3 85.1 / 368 m 23 07 Oct 2026 — Drilling
MTA2629 R205 HQ3 0 / 399 m 0 — — Planned
MTA2630 R204 HQ3 0 / 400 m 0 — — Planned
MTA2631 R205 HQ3 0 / 397 m 0 — — Planned
MTA2632 R204 HQ3 0 / 388 m 0 — — Planned
MTA2633 R205 HQ3 0 / 345 m 0 — — Planned
MTA2634 R204 HQ3 0 / 364 m 0 — — Planned
MTA2635 R205 HQ3 0 / 339 m 0 — — Planned
MTA2636 R204 HQ3 0 / 395 m 0 — — Planned
MTA2637 R205 HQ3 0 / 392 m 0 — — Planned
Latest drill reportsAll →
ReportShiftRigHoleMetresStby hValueStatus
DDR-243788 Oct nightR204MTA262834.50—Submitted
DDR-243778 Oct dayR204MTA262844.01.5—Submitted
DDR-243768 Oct dayR205MTA261949.20—Submitted
DDR-243677 Oct nightR204MTA262829.90$5,601Approved
DDR-243667 Oct dayR204MTA262855.20$10,246Approved
DDR-243657 Oct dayR205MTA261953.80$9,842Approved
DDR-243566 Oct nightR204MTA262620.52.5$5,550Approved
DDR-243556 Oct dayR204MTA262649.90$9,354Approved
DDR-243546 Oct dayR205MTA261950.90$9,067Approved
DDR-243455 Oct nightR204MTA262630.60$5,721Approved
DDR-243445 Oct dayR204MTA262643.90$8,018Approved
DDR-243435 Oct dayR205MTA261946.30$8,250Approved
DDR-243344 Oct nightR204MTA262644.80$8,311Approved · invoiced
DDR-243334 Oct dayR204MTA262646.30$8,526Approved · invoiced
DDR-243324 Oct dayR205MTA261941.20$7,760Approved · invoiced
DDR-243283 Oct nightR204MTA262650.90$9,412Approved · invoiced
Schedule of rateswhat every drill report is valued against
CodeDescriptionUnitRateApplied to
MOB-CORE Mobilise & demobilise — core rig lump $16,500.00 lump
DRL-HQ HQ3 wireline core 0–300 m m $172.00 metre
DRL-HQ300 HQ3 wireline core 300–600 m m $196.00 metre>300
STBY Standby — rig & crew hr $395.00 standby
MOVE Rig move between holes hr $430.00 move
WATER Water cartage hr $138.00 water
CT-HQ Core trays — HQ ea $26.00 item:CT-HQ
Client
BHP Mt Arthur Coal
Site
Mt Arthur Coal — North pit exploration
Client rep
Rebecca Lang
PO
4500873211
Terms
30 days EOM
Supervisor
Craig Morrison
Dates
25 Aug 2026 – 11 Dec 2026
Rigs
R204R205
Site access: Report to the Exploration office at the MIA. BHP induction + Coal Board Medical required. Radio channel 14.