← Projects On standby Large diameter 311 mm · HV electrical service holes · Muswellbrook depot All drill reports Rig app
Metres drilled (approved)
348 / 540 m
64% · 1 of 3 holes complete
Contract value
$254,864
ex GST
Earned to date
$171,892
15 approved shifts
Margin to date
48.1%
$82,618 after crew, rig & consumables
Standby
69.5 h
96 h drilling
Ready to invoice — 3 approved shifts not yet billed · invoiced to date $168,272 $15,870
Holes1 complete · 1 drilling · 1 planned
| Hole | Rig | Size | Depth | % | Collared | Completed | Status | |
|---|---|---|---|---|---|---|---|---|
| ULW001 | R215 | 311 mm | 180 / 180 m | 100 | 21 Sep 2026 | 25 Sep 2026 | Complete | |
| ULW002 | R215 | 311 mm | 167.7 / 180 m | 93 | 26 Sep 2026 | — | Drilling | |
| ULW003 | R215 | 311 mm | 0 / 180 m | 0 | — | — | Planned | |
Latest drill reportsAll →
| Report | Shift | Rig | Hole | Metres | Stby h | Value | Status |
|---|---|---|---|---|---|---|---|
| DDR-24374 | 8 Oct day | R215 | ULW002 | 0.0 | 11.5 | — | Submitted |
| DDR-24363 | 7 Oct day | R215 | ULW002 | 0.0 | 11.5 | $5,290 | Approved |
| DDR-24352 | 6 Oct day | R215 | ULW002 | 0.0 | 11.5 | $5,290 | Approved |
| DDR-24341 | 5 Oct day | R215 | ULW002 | 0.0 | 11.5 | $5,290 | Approved |
| DDR-24324 | 3 Oct day | R215 | ULW002 | 0.0 | 11.5 | $5,290 | Approved · invoiced |
| DDR-24313 | 2 Oct day | R215 | ULW002 | 0.0 | 11.5 | $5,290 | Approved · invoiced |
| DDR-24302 | 1 Oct day | R215 | ULW002 | 21.2 | 6 | $11,134 | Approved · invoiced |
| DDR-24291 | 30 Sep day | R215 | ULW002 | 20.7 | 6 | $10,937 | Approved · invoiced |
| DDR-24280 | 29 Sep day | R215 | ULW002 | 29.8 | 0 | $11,771 | Approved · invoiced |
| DDR-24270 | 28 Sep day | R215 | ULW002 | 41.5 | 0 | $16,393 | Approved · invoiced |
| DDR-24254 | 26 Sep day | R215 | ULW002 | 54.5 | 0 | $21,528 | Approved · invoiced |
| DDR-24244 | 25 Sep day | R215 | ULW001 | 43.4 | 0 | $17,143 | Approved · invoiced |
| DDR-24233 | 24 Sep day | R215 | ULW001 | 41.2 | 0 | $16,274 | Approved · invoiced |
| DDR-24222 | 23 Sep day | R215 | ULW001 | 41.7 | 0 | $16,472 | Approved · invoiced |
| DDR-24211 | 22 Sep day | R215 | ULW001 | 38.8 | 0 | $15,326 | Approved · invoiced |
| DDR-24200 | 21 Sep day | R215 | ULW001 | 14.9 | 0 | $8,466 | Approved · invoiced |
Schedule of rateswhat every drill report is valued against
| Code | Description | Unit | Rate | Applied to | |
|---|---|---|---|---|---|
| MOB-LD | Mobilise & demobilise — large diameter rig | lump | $24,500.00 | lump | |
| DRL-LD311 | Large diameter 311 mm | m | $395.00 | metre | |
| STBY | Standby — rig & crew | hr | $460.00 | standby | |
| MOVE | Rig move between holes | hr | $430.00 | move | |
- Client
- Glencore Coal Assets Australia
- Site
- Ulan Coal — Ulan West
- Client rep
- Andrew Kempe
- PO
- GCAA-7781377
- Terms
- 45 days EOM
- Supervisor
- Warren Kelly
- Dates
- 21 Sep 2026 – 30 Oct 2026
- Rigs
- R215
Site access: Permit to excavate needed before HV holes collar. Camp at Gulgong.
On standby since 30 Sep — Glencore permit to excavate for ULW002 not yet issued. Standby billed per contract.