← Projects Drilling Large diameter 216 mm · Gas drainage · Muswellbrook depot All drill reports Rig app
Metres drilled (approved)
1,721 / 2,520 m
68% · 4 of 6 holes complete
Contract value
$827,372
ex GST
Earned to date
$531,592
37 approved shifts
Margin to date
47.7%
$253,703 after crew, rig & consumables
Standby
17 h
387 h drilling
Ready to invoice — 3 approved shifts not yet billed · invoiced to date $511,230 $32,612
Holes4 complete · 1 drilling · 1 planned
| Hole | Rig | Size | Depth | % | Collared | Completed | Status | |
|---|---|---|---|---|---|---|---|---|
| MXG001 | R212 | 216 mm | 420 / 420 m | 100 | 01 Sep 2026 | 09 Sep 2026 | Complete | |
| MXG002 | R212 | 216 mm | 420 / 420 m | 100 | 10 Sep 2026 | 17 Sep 2026 | Complete | |
| MXG003 | R212 | 216 mm | 420 / 420 m | 100 | 18 Sep 2026 | 27 Sep 2026 | Complete | |
| MXG004 | R212 | 216 mm | 420 / 420 m | 100 | 28 Sep 2026 | 06 Oct 2026 | Complete | |
| MXG005 | R212 | 216 mm | 40.6 / 420 m | 10 | 07 Oct 2026 | — | Drilling | |
| MXG006 | R212 | 216 mm | 0 / 420 m | 0 | — | — | Planned | |
Latest drill reportsAll →
| Report | Shift | Rig | Hole | Metres | Stby h | Value | Status |
|---|---|---|---|---|---|---|---|
| DDR-24373 | 8 Oct day | R212 | MXG005 | 46.0 | 0 | — | Submitted |
| DDR-24362 | 7 Oct day | R212 | MXG005 | 40.6 | 0 | $12,391 | Approved |
| DDR-24351 | 6 Oct day | R212 | MXG004 | 1.2 | 0 | $2,849 | Approved |
| DDR-24340 | 5 Oct day | R212 | MXG004 | 54.6 | 2 | $17,372 | Approved |
| DDR-24331 | 4 Oct day | R212 | MXG004 | 41.2 | 0 | $12,154 | Approved · invoiced |
| DDR-24323 | 3 Oct day | R212 | MXG004 | 37.0 | 0 | $11,329 | Approved · invoiced |
| DDR-24312 | 2 Oct day | R212 | MXG004 | 64.9 | 0 | $19,353 | Approved · invoiced |
| DDR-24301 | 1 Oct day | R212 | MXG004 | 62.3 | 0 | $18,724 | Approved · invoiced |
| DDR-24290 | 30 Sep day | R212 | MXG004 | 49.8 | 0 | $15,036 | Approved · invoiced |
| DDR-24279 | 29 Sep day | R212 | MXG004 | 43.6 | 0 | $12,862 | Approved · invoiced |
| DDR-24269 | 28 Sep day | R212 | MXG004 | 65.4 | 1 | $19,753 | Approved · invoiced |
| DDR-24260 | 27 Sep day | R212 | MXG003 | 7.5 | 0 | $4,570 | Approved · invoiced |
| DDR-24253 | 26 Sep day | R212 | MXG003 | 55.4 | 0 | $16,757 | Approved · invoiced |
| DDR-24243 | 25 Sep day | R212 | MXG003 | 27.6 | 3 | $9,867 | Approved · invoiced |
| DDR-24232 | 24 Sep day | R212 | MXG003 | 38.6 | 0 | $11,663 | Approved · invoiced |
| DDR-24221 | 23 Sep day | R212 | MXG003 | 62.3 | 0 | $18,655 | Approved · invoiced |
Schedule of rateswhat every drill report is valued against
| Code | Description | Unit | Rate | Applied to | |
|---|---|---|---|---|---|
| MOB-LD | Mobilise & demobilise — large diameter rig | lump | $24,500.00 | lump | |
| DRL-LD216 | Large diameter 216 mm PDC | m | $295.00 | metre | |
| STBY | Standby — rig & crew | hr | $460.00 | standby | |
| MOVE | Rig move between holes | hr | $430.00 | move | |
| WATER | Water cartage | hr | $138.00 | water | |
- Client
- Malabar Resources
- Site
- Maxwell Underground — Woodlands Hill
- Client rep
- Sophie Turnbull
- PO
- MR-PO-3402
- Terms
- 30 days
- Supervisor
- Craig Morrison
- Dates
- 01 Sep 2026 – 27 Nov 2026
- Rigs
- R212
Site access: Gas test atmospheres ticket required for every crew member on gas drainage.