Metres drilled (approved)
583 / 1,680 m
35% · 4 of 14 holes complete
Contract value
$473,729
ex GST
Earned to date
$161,128
26 approved shifts
Margin to date
18.8%
$30,344 after crew, rig & consumables
Standby
12 h
274 h drilling
Ready to invoice — 3 approved shifts not yet billed · invoiced to date $147,732 $21,646
Holes4 complete · 1 drilling · 9 planned
| Hole | Rig | Size | Depth | % | Collared | Completed | Status | |
|---|---|---|---|---|---|---|---|---|
| MOC001 | R201 | PQ3 | 120 / 120 m | 100 | 08 Sep 2026 | 14 Sep 2026 | Complete | |
| MOC002 | R201 | PQ3 | 120 / 120 m | 100 | 15 Sep 2026 | 19 Sep 2026 | Complete | |
| MOC003 | R201 | PQ3 | 120 / 120 m | 100 | 21 Sep 2026 | 26 Sep 2026 | Complete | |
| MOC004 | R201 | PQ3 | 120 / 120 m | 100 | 28 Sep 2026 | 02 Oct 2026 | Complete | |
| MOC005 | R201 | PQ3 | 103 / 120 m | 86 | 03 Oct 2026 | — | Drilling | |
| MOC006 | R201 | PQ3 | 0 / 120 m | 0 | — | — | Planned | |
| MOC007 | R201 | PQ3 | 0 / 120 m | 0 | — | — | Planned | |
| MOC008 | R201 | PQ3 | 0 / 120 m | 0 | — | — | Planned | |
| MOC009 | R201 | PQ3 | 0 / 120 m | 0 | — | — | Planned | |
| MOC010 | R201 | PQ3 | 0 / 120 m | 0 | — | — | Planned | |
| MOC011 | R201 | PQ3 | 0 / 120 m | 0 | — | — | Planned | |
| MOC012 | R201 | PQ3 | 0 / 120 m | 0 | — | — | Planned | |
| MOC013 | R201 | PQ3 | 0 / 120 m | 0 | — | — | Planned | |
| MOC014 | R201 | PQ3 | 0 / 120 m | 0 | — | — | Planned | |
Latest drill reportsAll →
| Report | Shift | Rig | Hole | Metres | Stby h | Value | Status |
|---|---|---|---|---|---|---|---|
| DDR-24372 | 8 Oct day | R201 | MOC005 | 17.0 | 1 | — | Submitted |
| DDR-24361 | 7 Oct day | R201 | MOC005 | 28.3 | 0 | $7,452 | Approved |
| DDR-24350 | 6 Oct day | R201 | MOC005 | 20.1 | 2.5 | $6,339 | Approved |
| DDR-24339 | 5 Oct day | R201 | MOC005 | 29.9 | 0 | $7,855 | Approved |
| DDR-24322 | 3 Oct day | R201 | MOC005 | 24.7 | 1 | $6,932 | Approved · invoiced |
| DDR-24311 | 2 Oct day | R201 | MOC004 | 9.9 | 0 | $2,623 | Approved · invoiced |
| DDR-24300 | 1 Oct day | R201 | MOC004 | 26.5 | 0 | $6,966 | Approved · invoiced |
| DDR-24289 | 30 Sep day | R201 | MOC004 | 32.7 | 0 | $8,592 | Approved · invoiced |
| DDR-24278 | 29 Sep day | R201 | MOC004 | 18.4 | 0 | $4,861 | Approved · invoiced |
| DDR-24268 | 28 Sep day | R201 | MOC004 | 32.5 | 0 | $8,542 | Approved · invoiced |
| DDR-24252 | 26 Sep day | R201 | MOC003 | 14.3 | 0 | $3,764 | Approved · invoiced |
| DDR-24242 | 25 Sep day | R201 | MOC003 | 19.7 | 0 | $5,188 | Approved · invoiced |
| DDR-24231 | 24 Sep day | R201 | MOC003 | 15.6 | 2 | $4,963 | Approved · invoiced |
| DDR-24220 | 23 Sep day | R201 | MOC003 | 18.3 | 0 | $4,836 | Approved · invoiced |
| DDR-24209 | 22 Sep day | R201 | MOC003 | 29.1 | 0 | $7,653 | Approved · invoiced |
| DDR-24198 | 21 Sep day | R201 | MOC003 | 23.0 | 0 | $6,052 | Approved · invoiced |
Schedule of rateswhat every drill report is valued against
| Code | Description | Unit | Rate | Applied to | |
|---|---|---|---|---|---|
| MOB-CORE | Mobilise & demobilise — core rig | lump | $16,500.00 | lump | |
| DRL-PQ | PQ3 wireline core | m | $252.00 | metre | |
| STBY | Standby — rig & crew | hr | $420.00 | standby | |
| MOVE | Rig move between holes | hr | $430.00 | move | |
| CT-PQ | Core trays — PQ | ea | $32.00 | item:CT-PQ | |
- Client
- Yancoal Australia
- Site
- Moolarben Coal — OC4
- Client rep
- Priya Nair
- PO
- 4700-23190
- Terms
- 30 days EOM
- Supervisor
- Warren Kelly
- Dates
- 08 Sep 2026 – 06 Nov 2026
- Rigs
- R201
Site access: Yancoal induction. Core to the Moolarben core shed daily.