Kerembla

KQ-26-138

Idemitsu Australia — Water supply bores × 3 — Boggabri
Xero · synced 09:14 Demo 09 Oct 2026
← TendersPricing
Price build-upfrom the schedule of rates — edit any line
CodeDescriptionQtyUnitRateAmountMargin
MOB-WB Mobilise & demobilise — water bore rig 1 lump $9,500.00 $9,500.00 41%
DRL-WB Rotary — 250 mm water bore 450 m $210.00 $94,500.00 34%
STBY Standby — rig & crew 18 hr $420.00 $7,560.00 45%
MOVE Rig move between holes 12 hr $430.00 $5,160.00 45%
CAS-STL 200 mm steel casing 270 m $118.00 $31,860.00 47%
GRAVEL Gravel pack 90 bag $38.00 $3,420.00 63%
GROUT Cement grout 110 bag $29.00 $3,190.00 62%
CAMP Accommodation & meals 90 person-night $165.00 $14,850.00 27%
Client
Idemitsu Australia
Site
Boggabri Coal
Attention
Marcus Ellery
Method
Rotary — water bore
Scope
3 holes · 450 m · ~11 rig shifts
Rig
R210
Source
Phone
Due
20 Oct 2026
Prepared by
Matt Rourke
Subtotal (ex GST)$170,040.00 GST$17,004.00 Total inc GST$187,044.00 All-in per metre$377.87
Estimated margin 38.3% $65,064
Kerembla Pty Ltd
Kerembla Pty Ltd
6-8 Carramere Rd, Muswellbrook NSW 2333 · 0400 703 805 · info@kerembla.com.au
ABN 48 137 960 215
Quotation
KQ-26-138
Date 05 Oct 2026
Valid until 04 Dec 2026
Prepared by Matt Rourke
Quotation to
Idemitsu Australia
Attn: Marcus Ellery
Site: Boggabri Coal
Leard Forest Rd, Boggabri NSW 2382
ABN 54 866 147 849
Rotary — water bore · 3 holes · 450 m
Water supply bores × 3 — Boggabri
Proposed start 01 Feb 2027
ItemDescriptionQtyRateAmount
MOB-WBMobilise & demobilise — water bore rig1 lump$9,500.00$9,500.00
DRL-WBRotary — 250 mm water bore450 m$210.00$94,500.00
STBYStandby — rig & crew18 hr$420.00$7,560.00
MOVERig move between holes12 hr$430.00$5,160.00
CAS-STL200 mm steel casing270 m$118.00$31,860.00
GRAVELGravel pack90 bag$38.00$3,420.00
GROUTCement grout110 bag$29.00$3,190.00
CAMPAccommodation & meals90 person-night$165.00$14,850.00
Subtotal (ex GST)$170,040.00
GST 10%$17,004.00
Total (inc GST)$187,044.00
Rates are ex GST and valid for 60 days. Standby is charged when the rig and crew are on site and unable to drill for reasons outside Kerembla's control. Mobilisation and demobilisation are charged once per program. Consumables used in bore construction are charged at the listed rates. All work is carried out under Kerembla's Safety Management System and the site's principal hazard management plans.
Mineral exploration & water drilling · Large diameter drilling · Support services · Equipment dry hire