Price build-upfrom the schedule of rates — edit any line
| Code | Description | Qty | Unit | Rate | Amount | Margin | |
|---|---|---|---|---|---|---|---|
| MOB-RC | Mobilise & demobilise — RC rig | 1 | lump | $18,000.00 | $18,000.00 | 41% | |
| DRL-RC | RC 5½" face-sampling hammer | 4,200 | m | $91.00 | $382,200.00 | 34% | |
| STBY | Standby — rig & crew | 60 | hr | $420.00 | $25,200.00 | 45% | |
| MOVE | Rig move between holes | 84 | hr | $430.00 | $36,120.00 | 45% | |
- Client
- Alkane Resources
- Site
- Tomingley Gold Operations
- Attention
- Kate O'Sullivan
- Method
- RC
- Scope
- 28 holes · 4,200 m · ~30 rig shifts
- Rig
- R218
- Source
- Repeat client
- Due
- 09 Oct 2026
- Prepared by
- Ross Gallagher
Subtotal (ex GST)$461,520.00 GST$46,152.00 Total inc GST$507,672.00 All-in per metre$109.89
Estimated margin 35.7% $164,942
Notes
Alkane asked for RC rates held to 30 June 2027.
Kerembla Pty Ltd
6-8 Carramere Rd, Muswellbrook NSW 2333 · 0400 703 805 · info@kerembla.com.au
ABN 48 137 960 215
Quotation
KQ-26-135
Date 25 Sep 2026
Valid until 24 Nov 2026
Prepared by Ross Gallagher
Quotation to
Alkane Resources
Attn: Kate O'Sullivan
Site: Tomingley Gold Operations
1 Tomingley Rd, Tomingley NSW 2869
ABN 24 178 478 749
RC · 28 holes · 4,200 m
Roswell exploration — RC programProposed start 11 Jan 2027
| Item | Description | Qty | Rate | Amount |
|---|---|---|---|---|
| MOB-RC | Mobilise & demobilise — RC rig | 1 lump | $18,000.00 | $18,000.00 |
| DRL-RC | RC 5½" face-sampling hammer | 4,200 m | $91.00 | $382,200.00 |
| STBY | Standby — rig & crew | 60 hr | $420.00 | $25,200.00 |
| MOVE | Rig move between holes | 84 hr | $430.00 | $36,120.00 |
| Subtotal (ex GST) | $461,520.00 |
| GST 10% | $46,152.00 |
| Total (inc GST) | $507,672.00 |
Alkane asked for RC rates held to 30 June 2027.
Rates are ex GST and valid for 60 days. Standby is charged when the rig and crew are on site and unable to drill for reasons outside Kerembla's control. Mobilisation and demobilisation are charged once per program. Consumables used in bore construction are charged at the listed rates. All work is carried out under Kerembla's Safety Management System and the site's principal hazard management plans.