Kerembla

DDR-24362

R212 · 07 Oct 2026 day shift · KP-26-036 Malabar Resources
Xero · synced 09:14 Demo 09 Oct 2026
← Drill reports KP-26-036
ShiftMaxwell Underground — Woodlands Hill
Rig
R212 Foremost FH3000
Hole
MXG005 · 216 mm
Depth
0 → 40.6 m · 40.6 m
Hours
Drilling 11.5 · standby 0 · rig move 0 · maintenance 0.5 · water cart 3
Submitted
07 Oct 2026 · 18:13
Client sign-off
Sophie Turnbull
Consumablesdrawn from Muswellbrook
ItemQtyCost
MUD-FOAM Drilling foam 20 L3 drum$354.00
MUD-PHPA PHPA liquid polymer 20 L2 drum$284.00
FUEL Diesel — bulk756 L$1,270.08
Billing at the schedule of rates$12,391.00
CodeDescriptionQtyRateAmount
DRL-LD216Large diameter 216 mm PDC40.6 m$295.00$11,977.00
WATERWater cartage3 hr$138.00$414.00
Crew
Corey Albrecht
Driller · 8 ord + 4 OT · 1.5 travel
12 h
Jordan Vella
Offsider · 8 ord + 4 OT · 1.5 travel
12 h
Lachlan Gould
Offsider · 8 ord + 4 OT · 1.5 travel
12 h
Shift economics
Value at contract rates$12,391.00 Crew, rig hours & consumables$7,422.50 Shift margin$4,968.50 · 40.1%