← Projects Drilling Large diameter 311 mm · Goaf drainage · Muswellbrook depot All drill reports Rig app
Metres drilled (approved)
792 / 1,160 m
68% · 2 of 4 holes complete
Contract value
$506,828
ex GST
Earned to date
$323,950
24 approved shifts
Margin to date
41.7%
$135,030 after crew, rig & consumables
Standby
18 h
243.5 h drilling
Ready to invoice — 3 approved shifts not yet billed · invoiced to date $295,561 $40,639
Holes2 complete · 1 drilling · 1 planned
| Hole | Rig | Size | Depth | % | Collared | Completed | Status | |
|---|---|---|---|---|---|---|---|---|
| WSB001 | R213 | 311 mm | 290 / 290 m | 100 | 14 Sep 2026 | 21 Sep 2026 | Complete | |
| WSB002 | R213 | 311 mm | 290 / 290 m | 100 | 22 Sep 2026 | 01 Oct 2026 | Complete | |
| WSB003 | R213 | 311 mm | 212.3 / 290 m | 73 | 02 Oct 2026 | — | Drilling | |
| WSB004 | R213 | 311 mm | 0 / 290 m | 0 | — | — | Planned | |
Latest drill reportsAll →
| Report | Shift | Rig | Hole | Metres | Stby h | Value | Status |
|---|---|---|---|---|---|---|---|
| DDR-24371 | 8 Oct day | R213 | WSB003 | 45.9 | 0 | — | Submitted |
| DDR-24360 | 7 Oct day | R213 | WSB003 | 27.1 | 2 | $11,274 | Approved |
| DDR-24349 | 6 Oct day | R213 | WSB003 | 37.3 | 0 | $14,637 | Approved |
| DDR-24338 | 5 Oct day | R213 | WSB003 | 35.0 | 2 | $14,729 | Approved |
| DDR-24330 | 4 Oct day | R213 | WSB003 | 41.6 | 0 | $16,292 | Approved · invoiced |
| DDR-24321 | 3 Oct day | R213 | WSB003 | 34.4 | 0 | $13,658 | Approved · invoiced |
| DDR-24310 | 2 Oct day | R213 | WSB003 | 36.9 | 0 | $14,414 | Approved · invoiced |
| DDR-24299 | 1 Oct day | R213 | WSB002 | 23.2 | 0 | $9,277 | Approved · invoiced |
| DDR-24288 | 30 Sep day | R213 | WSB002 | 37.7 | 0 | $14,791 | Approved · invoiced |
| DDR-24277 | 29 Sep day | R213 | WSB002 | 34.9 | 0 | $13,437 | Approved · invoiced |
| DDR-24267 | 28 Sep day | R213 | WSB002 | 30.2 | 0 | $11,903 | Approved · invoiced |
| DDR-24259 | 27 Sep day | R213 | WSB002 | 29.0 | 0 | $11,579 | Approved · invoiced |
| DDR-24251 | 26 Sep day | R213 | WSB002 | 18.9 | 4 | $9,233 | Approved · invoiced |
| DDR-24241 | 25 Sep day | R213 | WSB002 | 34.3 | 0 | $13,620 | Approved · invoiced |
| DDR-24230 | 24 Sep day | R213 | WSB002 | 29.7 | 4 | $13,460 | Approved · invoiced |
| DDR-24219 | 23 Sep day | R213 | WSB002 | 24.4 | 4 | $11,419 | Approved · invoiced |
Schedule of rateswhat every drill report is valued against
| Code | Description | Unit | Rate | Applied to | |
|---|---|---|---|---|---|
| MOB-LD | Mobilise & demobilise — large diameter rig | lump | $24,500.00 | lump | |
| DRL-LD311 | Large diameter 311 mm | m | $385.00 | metre | |
| STBY | Standby — rig & crew | hr | $420.00 | standby | |
| MOVE | Rig move between holes | hr | $430.00 | move | |
| WATER | Water cartage | hr | $138.00 | water | |
- Client
- Peabody Energy Australia
- Site
- Wambo Coal — South Bates
- Client rep
- Glen Hutchins
- PO
- PEA-118274
- Terms
- 30 days EOM
- Supervisor
- Craig Morrison
- Dates
- 14 Sep 2026 – 13 Nov 2026
- Rigs
- R213
Site access: Gas monitoring on every goaf hole. Peabody induction.