Kerembla

KP-26-039

Peabody Energy Australia — Goaf drainage holes — South Bates LW 21
Xero · synced 09:14 Demo 09 Oct 2026
← Projects Drilling Large diameter 311 mm · Goaf drainage · Muswellbrook depot
All drill reports Rig app
Metres drilled (approved)
792 / 1,160 m
68% · 2 of 4 holes complete
Contract value
$506,828
ex GST
Earned to date
$323,950
24 approved shifts
Margin to date
41.7%
$135,030 after crew, rig & consumables
Standby
18 h
243.5 h drilling
Ready to invoice — 3 approved shifts not yet billed · invoiced to date $295,561 $40,639
Holes2 complete · 1 drilling · 1 planned
HoleRigSizeDepth%CollaredCompletedStatus
WSB001 R213 311 mm 290 / 290 m 100 14 Sep 2026 21 Sep 2026 Complete
WSB002 R213 311 mm 290 / 290 m 100 22 Sep 2026 01 Oct 2026 Complete
WSB003 R213 311 mm 212.3 / 290 m 73 02 Oct 2026 — Drilling
WSB004 R213 311 mm 0 / 290 m 0 — — Planned
Latest drill reportsAll →
ReportShiftRigHoleMetresStby hValueStatus
DDR-243718 Oct dayR213WSB00345.90—Submitted
DDR-243607 Oct dayR213WSB00327.12$11,274Approved
DDR-243496 Oct dayR213WSB00337.30$14,637Approved
DDR-243385 Oct dayR213WSB00335.02$14,729Approved
DDR-243304 Oct dayR213WSB00341.60$16,292Approved · invoiced
DDR-243213 Oct dayR213WSB00334.40$13,658Approved · invoiced
DDR-243102 Oct dayR213WSB00336.90$14,414Approved · invoiced
DDR-242991 Oct dayR213WSB00223.20$9,277Approved · invoiced
DDR-2428830 Sep dayR213WSB00237.70$14,791Approved · invoiced
DDR-2427729 Sep dayR213WSB00234.90$13,437Approved · invoiced
DDR-2426728 Sep dayR213WSB00230.20$11,903Approved · invoiced
DDR-2425927 Sep dayR213WSB00229.00$11,579Approved · invoiced
DDR-2425126 Sep dayR213WSB00218.94$9,233Approved · invoiced
DDR-2424125 Sep dayR213WSB00234.30$13,620Approved · invoiced
DDR-2423024 Sep dayR213WSB00229.74$13,460Approved · invoiced
DDR-2421923 Sep dayR213WSB00224.44$11,419Approved · invoiced
Schedule of rateswhat every drill report is valued against
CodeDescriptionUnitRateApplied to
MOB-LD Mobilise & demobilise — large diameter rig lump $24,500.00 lump
DRL-LD311 Large diameter 311 mm m $385.00 metre
STBY Standby — rig & crew hr $420.00 standby
MOVE Rig move between holes hr $430.00 move
WATER Water cartage hr $138.00 water
Client
Peabody Energy Australia
Site
Wambo Coal — South Bates
Client rep
Glen Hutchins
PO
PEA-118274
Terms
30 days EOM
Supervisor
Craig Morrison
Dates
14 Sep 2026 – 13 Nov 2026
Rigs
R213
Site access: Gas monitoring on every goaf hole. Peabody induction.