KP-26-042

Idemitsu Australia — Fault delineation — HQ3 core
Xero · synced 09:14 Demo 09 Oct 2026
← Projects Drilling HQ3 core · Fault de-lineation · Muswellbrook depot
All drill reports Rig app
Metres drilled (approved)
819 / 1,760 m
47% · 3 of 8 holes complete
Contract value
$354,842
ex GST
Earned to date
$159,843
23 approved shifts
Margin to date
29.3%
$46,756 after crew, rig & consumables
Standby
10.5 h
239.5 h drilling
Ready to invoice — 2 approved shifts not yet billed · invoiced to date $150,788 $17,305
Holes3 complete · 1 drilling · 4 planned
HoleRigSizeDepth%CollaredCompletedStatus
BGF001 R208 HQ3 220 / 220 m 100 14 Sep 2026 20 Sep 2026 Complete
BGF002 R208 HQ3 220 / 220 m 100 21 Sep 2026 26 Sep 2026 Complete
BGF003 R208 HQ3 220 / 220 m 100 27 Sep 2026 02 Oct 2026 Complete
BGF004 R208 HQ3 158.6 / 220 m 72 03 Oct 2026 — Drilling
BGF005 R208 HQ3 0 / 220 m 0 — — Planned
BGF006 R208 HQ3 0 / 220 m 0 — — Planned
BGF007 R208 HQ3 0 / 220 m 0 — — Planned
BGF008 R208 HQ3 0 / 220 m 0 — — Planned
Latest drill reportsAll →
ReportShiftRigHoleMetresStby hValueStatus
DDR-243688 Oct dayR208BGF00412.20—Submitted
DDR-243577 Oct dayR208BGF00449.23.5—Queried
DDR-243466 Oct dayR208BGF00449.10$9,026Approved
DDR-243355 Oct dayR208BGF00439.32.5$8,279Approved
DDR-243294 Oct dayR208BGF00435.80$6,580Approved · invoiced
DDR-243183 Oct dayR208BGF00434.40$6,331Approved · invoiced
DDR-243072 Oct dayR208BGF00315.90$2,934Approved · invoiced
DDR-242961 Oct dayR208BGF00328.23$6,462Approved · invoiced
DDR-2428530 Sep dayR208BGF00329.20$5,380Approved · invoiced
DDR-2427429 Sep dayR208BGF00347.90$8,812Approved · invoiced
DDR-2426428 Sep dayR208BGF00355.30$10,181Approved · invoiced
DDR-2425827 Sep dayR208BGF00343.50$8,003Approved · invoiced
DDR-2424826 Sep dayR208BGF00242.20$7,772Approved · invoiced
DDR-2423825 Sep dayR208BGF00229.30$5,397Approved · invoiced
DDR-2422724 Sep dayR208BGF00242.40$7,807Approved · invoiced
DDR-2421623 Sep dayR208BGF00230.74$7,327Approved · invoiced
Schedule of rateswhat every drill report is valued against
CodeDescriptionUnitRateApplied to
MOB-CORE Mobilise & demobilise — core rig lump $16,500.00 lump
DRL-HQ HQ3 wireline core 0–300 m m $178.00 metre
STBY Standby — rig & crew hr $420.00 standby
MOVE Rig move between holes hr $430.00 move
CT-HQ Core trays — HQ ea $26.00 item:CT-HQ
Client
Idemitsu Australia
Site
Boggabri Coal
Client rep
Marcus Ellery
PO
IA-0098812
Terms
30 days EOM
Supervisor
Warren Kelly
Dates
14 Sep 2026 – 20 Nov 2026
Rigs
R208
Site access: 2 h 40 from Muswellbrook depot — crew camp in Boggabri.