Metres drilled (approved)
819 / 1,760 m
47% · 3 of 8 holes complete
Contract value
$354,842
ex GST
Earned to date
$159,843
23 approved shifts
Margin to date
29.3%
$46,756 after crew, rig & consumables
Standby
10.5 h
239.5 h drilling
Ready to invoice — 2 approved shifts not yet billed · invoiced to date $150,788 $17,305
Holes3 complete · 1 drilling · 4 planned
| Hole | Rig | Size | Depth | % | Collared | Completed | Status | |
|---|---|---|---|---|---|---|---|---|
| BGF001 | R208 | HQ3 | 220 / 220 m | 100 | 14 Sep 2026 | 20 Sep 2026 | Complete | |
| BGF002 | R208 | HQ3 | 220 / 220 m | 100 | 21 Sep 2026 | 26 Sep 2026 | Complete | |
| BGF003 | R208 | HQ3 | 220 / 220 m | 100 | 27 Sep 2026 | 02 Oct 2026 | Complete | |
| BGF004 | R208 | HQ3 | 158.6 / 220 m | 72 | 03 Oct 2026 | — | Drilling | |
| BGF005 | R208 | HQ3 | 0 / 220 m | 0 | — | — | Planned | |
| BGF006 | R208 | HQ3 | 0 / 220 m | 0 | — | — | Planned | |
| BGF007 | R208 | HQ3 | 0 / 220 m | 0 | — | — | Planned | |
| BGF008 | R208 | HQ3 | 0 / 220 m | 0 | — | — | Planned | |
Latest drill reportsAll →
| Report | Shift | Rig | Hole | Metres | Stby h | Value | Status |
|---|---|---|---|---|---|---|---|
| DDR-24368 | 8 Oct day | R208 | BGF004 | 12.2 | 0 | — | Submitted |
| DDR-24357 | 7 Oct day | R208 | BGF004 | 49.2 | 3.5 | — | Queried |
| DDR-24346 | 6 Oct day | R208 | BGF004 | 49.1 | 0 | $9,026 | Approved |
| DDR-24335 | 5 Oct day | R208 | BGF004 | 39.3 | 2.5 | $8,279 | Approved |
| DDR-24329 | 4 Oct day | R208 | BGF004 | 35.8 | 0 | $6,580 | Approved · invoiced |
| DDR-24318 | 3 Oct day | R208 | BGF004 | 34.4 | 0 | $6,331 | Approved · invoiced |
| DDR-24307 | 2 Oct day | R208 | BGF003 | 15.9 | 0 | $2,934 | Approved · invoiced |
| DDR-24296 | 1 Oct day | R208 | BGF003 | 28.2 | 3 | $6,462 | Approved · invoiced |
| DDR-24285 | 30 Sep day | R208 | BGF003 | 29.2 | 0 | $5,380 | Approved · invoiced |
| DDR-24274 | 29 Sep day | R208 | BGF003 | 47.9 | 0 | $8,812 | Approved · invoiced |
| DDR-24264 | 28 Sep day | R208 | BGF003 | 55.3 | 0 | $10,181 | Approved · invoiced |
| DDR-24258 | 27 Sep day | R208 | BGF003 | 43.5 | 0 | $8,003 | Approved · invoiced |
| DDR-24248 | 26 Sep day | R208 | BGF002 | 42.2 | 0 | $7,772 | Approved · invoiced |
| DDR-24238 | 25 Sep day | R208 | BGF002 | 29.3 | 0 | $5,397 | Approved · invoiced |
| DDR-24227 | 24 Sep day | R208 | BGF002 | 42.4 | 0 | $7,807 | Approved · invoiced |
| DDR-24216 | 23 Sep day | R208 | BGF002 | 30.7 | 4 | $7,327 | Approved · invoiced |
Schedule of rateswhat every drill report is valued against
| Code | Description | Unit | Rate | Applied to | |
|---|---|---|---|---|---|
| MOB-CORE | Mobilise & demobilise — core rig | lump | $16,500.00 | lump | |
| DRL-HQ | HQ3 wireline core 0–300 m | m | $178.00 | metre | |
| STBY | Standby — rig & crew | hr | $420.00 | standby | |
| MOVE | Rig move between holes | hr | $430.00 | move | |
| CT-HQ | Core trays — HQ | ea | $26.00 | item:CT-HQ | |
- Client
- Idemitsu Australia
- Site
- Boggabri Coal
- Client rep
- Marcus Ellery
- PO
- IA-0098812
- Terms
- 30 days EOM
- Supervisor
- Warren Kelly
- Dates
- 14 Sep 2026 – 20 Nov 2026
- Rigs
- R208
Site access: 2 h 40 from Muswellbrook depot — crew camp in Boggabri.