Kerembla

KP-26-030

Malabar Resources — Concrete & ballast drop holes — Maxwell portal
Xero · synced 09:14 Demo 09 Oct 2026
← Projects Complete Large diameter 311 mm · Concrete and ballast drop holes · Muswellbrook depot
All drill reports Rig app
Metres drilled (approved)
435 / 435 m
100% · 3 of 3 holes complete
Contract value
$221,816
ex GST
Earned to date
$188,690
13 approved shifts
Margin to date
51.3%
$96,811 after crew, rig & consumables
Standby
3 h
134 h drilling
Ready to invoice — 0 approved shifts not yet billed · invoiced to date $200,940 $0
Holes3 complete · 0 drilling · 0 planned
HoleRigSizeDepth%CollaredCompletedStatus
MXD001 R213 311 mm 145 / 145 m 100 11 Aug 2026 14 Aug 2026 Complete
MXD002 R213 311 mm 145 / 145 m 100 15 Aug 2026 18 Aug 2026 Complete
MXD003 R213 311 mm 145 / 145 m 100 19 Aug 2026 23 Aug 2026 Complete
Latest drill reportsAll →
ReportShiftRigHoleMetresStby hValueStatus
DDR-2404423 Aug dayR213MXD0036.20$4,754Approved · invoiced
DDR-2404322 Aug dayR213MXD00331.71$13,734Approved · invoiced
DDR-2404121 Aug dayR213MXD00342.50$17,850Approved · invoiced
DDR-2403820 Aug dayR213MXD00326.40$11,088Approved · invoiced
DDR-2403519 Aug dayR213MXD00338.20$16,044Approved · invoiced
DDR-2403218 Aug dayR213MXD00229.90$12,558Approved · invoiced
DDR-2402917 Aug dayR213MXD00230.70$12,894Approved · invoiced
DDR-2402816 Aug dayR213MXD00243.90$18,438Approved · invoiced
DDR-2402515 Aug dayR213MXD00240.50$17,010Approved · invoiced
DDR-2402214 Aug dayR213MXD00129.52$13,230Approved · invoiced
DDR-2401913 Aug dayR213MXD00149.20$20,664Approved · invoiced
DDR-2401612 Aug dayR213MXD00140.30$16,926Approved · invoiced
DDR-2401311 Aug dayR213MXD00126.00$13,500Approved · invoiced
Schedule of rateswhat every drill report is valued against
CodeDescriptionUnitRateApplied to
MOB-LD Mobilise & demobilise — large diameter rig lump $24,500.00 lump
DRL-LD311 Large diameter 311 mm m $420.00 metre
STBY Standby — rig & crew hr $420.00 standby
MOVE Rig move between holes hr $430.00 move
Client
Malabar Resources
Site
Maxwell Underground — Woodlands Hill
Client rep
Sophie Turnbull
PO
MR-PO-3318
Terms
30 days
Supervisor
Craig Morrison
Dates
11 Aug 2026 – 30 Aug 2026
Rigs
R213
Site access: Gas test atmospheres ticket required for every crew member on gas drainage.
Final invoice issued.