Kerembla

KQ-26-118

BHP Mt Arthur Coal — North pit exploration infill — 28 × HQ3 diamond holes
Xero · synced 09:14 Demo 09 Oct 2026
← TendersWon
Won 06 Aug 2026 · 10:12 · Rebecca Lang · PO 4500873211KP-26-031 · Drilling →
Price build-upfrom the schedule of rates — edit any line
CodeDescriptionQtyRateAmount
MOB-COREMobilise & demobilise — core rig2 lump$16,500.00$33,000.00
DRL-HQHQ3 wireline core 0–300 m8,400 m$172.00$1,444,800.00
DRL-HQ300HQ3 wireline core 300–600 m1,680 m$196.00$329,280.00
STBYStandby — rig & crew180 hr$395.00$71,100.00
MOVERig move between holes170 hr$430.00$73,100.00
WATERWater cartage400 hr$138.00$55,200.00
CT-HQCore trays — HQ2,240 ea$26.00$58,240.00
SURVDownhole gyro survey28 hole$850.00$23,800.00
Client
BHP Mt Arthur Coal
Site
Mt Arthur Coal — North pit exploration
Attention
Rebecca Lang
Method
HQ3 core
Scope
28 holes · 10,080 m · ~258 rig shifts
Rig
R204
Source
Tender portal
Due
31 Jul 2026
Prepared by
Matt Rourke
Subtotal (ex GST)$2,088,520.00 GST$208,852.00 Total inc GST$2,297,372.00 All-in per metre$207.19
Estimated margin 35.6% $742,877
Kerembla Pty Ltd
Kerembla Pty Ltd
6-8 Carramere Rd, Muswellbrook NSW 2333 · 0400 703 805 · info@kerembla.com.au
ABN 48 137 960 215
Quotation
KQ-26-118
Date 14 Jul 2026
Valid until 12 Sep 2026
Prepared by Matt Rourke
Quotation to
BHP Mt Arthur Coal
Attn: Rebecca Lang
Site: Mt Arthur Coal — North pit exploration
Thomas Mitchell Dr, Muswellbrook NSW 2333
ABN 47 827 857 974
HQ3 core · 28 holes · 10,080 m
North pit exploration infill — 28 × HQ3 diamond holes
Proposed start 25 Aug 2026
ItemDescriptionQtyRateAmount
MOB-COREMobilise & demobilise — core rig2 lump$16,500.00$33,000.00
DRL-HQHQ3 wireline core 0–300 m8,400 m$172.00$1,444,800.00
DRL-HQ300HQ3 wireline core 300–600 m1,680 m$196.00$329,280.00
STBYStandby — rig & crew180 hr$395.00$71,100.00
MOVERig move between holes170 hr$430.00$73,100.00
WATERWater cartage400 hr$138.00$55,200.00
CT-HQCore trays — HQ2,240 ea$26.00$58,240.00
SURVDownhole gyro survey28 hole$850.00$23,800.00
Subtotal (ex GST)$2,088,520.00
GST 10%$208,852.00
Total (inc GST)$2,297,372.00
Rates are ex GST and valid for 60 days. Standby is charged when the rig and crew are on site and unable to drill for reasons outside Kerembla's control. Mobilisation and demobilisation are charged once per program. Consumables used in bore construction are charged at the listed rates. All work is carried out under Kerembla's Safety Management System and the site's principal hazard management plans.
Mineral exploration & water drilling · Large diameter drilling · Support services · Equipment dry hire